The state-owned coal-fired power plant, Maritza East 2, is embarking on an ambitious project to install solar panels on its administrative buildings, warehouses, parking lots, and other properties. This initiative has been announced through market consultations published by the Public Procurement Agency (PPA). Discussions regarding the power plant’s plans to develop photovoltaic installations for self-consumption have recently taken place in the National Assembly.
During a hearing, the acting Minister of Energy, Vladimir Malinov, mentioned that the Ministry of Energy (ME) is exploring this option. He indicated that a preliminary project for a solar park on the premises of Maritza East 2 is already in place, but it is contingent upon securing external grant funding, as there are currently no allocated resources for this venture. Despite financial constraints, the state enterprise aims to gather insights from the consultations regarding the estimated costs and timelines for the solar projects.
Planned Solar Installations
Documents released by the PPA reveal that the power plant has several solar projects in the pipeline. Among these, two are rooftop installations—one on the main administrative building and another on a parking facility for buses and cars. The proposed photovoltaic system on the primary administrative building is expected to have a peak capacity of 651.78 kWp, while another administrative building will feature an installation with a capacity of 172 kWp. Additional installations are planned for three warehouses with capacities of 239, 238, and 277 kWp, respectively, and another operational warehouse with a capacity of 320 kWp. Furthermore, a building housing a dewatering facility may also be outfitted with solar panels, boasting a capacity of 453.6 kWp.
Moreover, there is a project for a solar installation at a parking area designated for light vehicles and buses, located near the main entrance, which is projected to have a capacity of 925.02 kWp. The deadline for submitting bids for these two projects has already passed, and details are expected to be released soon.
Larger Solar Project on Plant Property
In addition to the rooftop projects, Maritza East 2 is planning a larger photovoltaic power plant on its own land. The announced investment aims to reduce electricity costs, limit harmful emissions, meet its consumption needs, and generate surplus electricity for sale in the free market. A working project is under development, which will be executed in sections from 1 to 7. Each section can be implemented independently but is designed to function synergistically once fully constructed:
- Part 1 – PV Plant on Land 1 with an area of 426.46 acres;
- Part 2 – PV Plant on Land 2 with an area of 401.66 acres;
- Part 3 – PV Plant on Land 3 with an area of 124.98 acres;
- Part 4 – PV Plant on Land 4 with an area of 49.36 acres;
- Part 5 – PV Plant on Land 5 with an area of 122.38 acres;
- Part 6 – A 110 kV substation capable of connecting all land’s full capacity and an energy storage system, along with an overhead power line connecting the 110 kV substation with the 110 kV distribution station owned by ESO EAD;
- Part 7 – A battery energy storage system with a capacity of 10MW/25MWh.
The consultation process for this larger project is still ongoing, allowing for the submission of offers.
“`
Introduction of Innovations as a Strategic Priority
In the documentation related to this initiative, it is clearly stated that “the implementation of innovative practices is a key focus for the management team, with anticipated outcomes including enhanced workflow efficiency and increased production, all while minimizing resource expenditure.”
Goals and Expectations
The primary objective behind this project is to foster a culture of innovation that not only boosts productivity but also streamlines operations. By embracing new technologies and methodologies, the organization aims to achieve significant improvements in its operational processes.
Resource Management
Another critical aspect highlighted in the documentation is the intention to reduce resource usage. By optimizing workflows and integrating innovative solutions, the organization seeks to lower costs while maintaining high standards of quality and efficiency.
Conclusion
In summary, the focus on innovation within this project underscores a commitment to continuous improvement and sustainable growth. The expected results are not just about increasing output but also about creating a more efficient and resource-conscious operational framework.